Switzerland

Rosshäusern Tunnel Breakthrough

An important phase has been completed in the construction of the approximately 2 km long, two-track Rosshäusern Tunnel on the line from Berne to Neuchâtel. After the decision to change the method of construction, the last blast took place in the upper half of the tunnel (top heading) 181 m west of the tunnel middle at the start of June 2015. After the breakthrough, the upper half of the tunnel will be refinished in the following three to four months, before the excavation of the lower half, the bench and the invert, is started in the autumn. The tunnel should be structurally complete in the middle of 2017.

The Rosshäusern Tunnel is the key structure in the two-track widening of the line from Rosshäusern to Mauss and makes up about half of the section. It will replace the original 1.1. km long single-track tunnel, which is 110 years old and in need of refurbishment. Excavation of the new tunnel started in spring 2013. Due to the difficult geological conditions, the method of tunnelling was changed in January 2014. Instead of full-face excavation from the east, the top heading was advanced first from east and from west. The change of tunnelling method in fractured rock has proved successful according to the owner company BLS AG; the works have made better progress than originally expected. The construction project has suffered a delay of about 18 with an increase of cost by 65 to about 265 million Swiss francs. The first trains should be able to travel on the new two-track line from the middle of 2018. / G.B.

x

Related articles:

Issue 05/2012 Switzerland

New Rosshäusern Tunnel for Route Development

The 43 km long, mainly single-track route Berne-Kerzers-Neuchâtel (1901) in the Cantons of Berne, Freiburg and Neuenburg is part of the Berne-Paris link and the Berne S-Bahn transit system. The BLS...

more
Issue 06/2014

Mode of Construction for the New Rosshäusern Tunnel changed

The new tunnel will replace the single-track old Rosshäusern Tunnel with its many bends, dating back to 1901, which could not be redeveloped for economic reasons. The old tunnel is also to be used as...

more
Issue 03/2024

SBB Dual-Track Tunnel Ligerz: Eliminating a Traffic Bottleneck With Complex Boundary Conditions

1 Introduction The SBB’s southern ridge-base line (Jurasüdfußlinie) runs from Geneva/Lausanne via Neuchâtel and Biel to Basel/Zurich. The cur- rent single-track line in the Ligerz–Twann section...

more
Issue 08/2010 Switzerland

Gotthard Base Tunnel: High-accuracy at final breakthrough

The tunnel-boring machine, affectionately dubbed „Sissi“, in honour of the 19th century Austrian empress, by the international team of tunnellers engaged on the project, completed the final...

more
Issue 03/2020 Germany

Stuttgart 21: Excavation of Feuerbach Tunnel Is Finished

Driving for the Feuerbach Tunnel, which connects the existing railway lines to and from Mannheim, Karlsruhe and Paris with the future Stuttgart Central Station, was completed with a tunnel...

more