Mode of Construction for the New Rosshäusern Tunnel changed

The 43 km long, largely single-track line between Berne and Neuchâtel in the Cantons of Berne, Freiburg and Neuenburg is part of the route from Berne to Paris. It is currently being developed with twin tracks by the private rail company BLS AG and will then be suitable for speeds of up to 160 km/h rather than the present 90 km/h. Work started on the Rosshäusern-Mauss section in 2012, which is also straightened and shortened by 300 m. The new 2080 m long, twin-track Rosshäusern Tunnel represents the core of this construction section.

The new tunnel will replace the single-track old Rosshäusern Tunnel with its many bends, dating back to 1901, which could not be redeveloped for economic reasons. The old tunnel is also to be used as a drainage tunnel as from 2018 after it has been properly adapted. Work on the new tunnel commenced in 2013 and it was originally scheduled to become operational at the end of 2016. Some 190 million Swiss francs (160 million euros) were earmarked for the overall costs of this major project including restoring the Flüelabach watercourse alongside the old line. The new tunnel with its...

Related articles:

Issue 05/2015 Switzerland

Rosshäusern Tunnel Breakthrough

An important phase has been completed in the construction of the approximately 2 km long, two-track Rosshäusern Tunnel on the line from Berne to Neuchâtel. After the decision to change the method of...

more
Issue 05/2012 Switzerland

New Rosshäusern Tunnel for Route Development

The 43 km long, mainly single-track route Berne-Kerzers-Neuchâtel (1901) in the Cantons of Berne, Freiburg and Neuenburg is part of the Berne-Paris link and the Berne S-Bahn transit system. The BLS...

more
Issue 05/2014 Switzerland

Swiss Tunnel Congress 2014

The Swiss Tunnelling Society (STS/FGU) of the Swiss Engineers and Architects Association (SIA) staged its conference, the Swiss Tunnel Congress (STC), in Lucerne on June 11 and 12, 2014 with reports...

more
Issue 08/2017

Eppenberg Tunnel: Convertible TBM for Rock and Soft Soil

The Eppenberg Tunnel with its connections to the existing track system is included in Lot A of the overall project. This project consists of the part-projects TP1 to TP3 and TP8, which are executed...

more
Issue 02/2018

New Bözberg Tunnel: Structural Measures when Tunnelling in squeezing Rock

1 Introduction The new Bözberg Tunnel with a total length of roughly 2.7 km is the longest single element among the structures on the 4-Metre Corridor, which were largely driven mechanically using a...