New Bözberg Tunnel: Structural Measures when Tunnelling in squeezing Rock

The new Bözberg Tunnel is part of the so-called “4-Metre Corridor” on the northern access route to the new Gotthard Base Tunnel. After the new tunnel has been completed, freight can be transported in combined mode with a corner height of 4 m on the Gotthard artery through Switzerland and in turn, on the important Rhine-Alps goods train corridor as from the 2020/2021 modified timetable. The existing Bözberg Tunnel dating back to 1875 is not capable of coping with the required clearance profile and is being replaced by a twin-track tunnel that runs parallel to it. This possesses a considerably greater clearance profile in accordance with EBV 4/S3. The existing tunnel will be converted for use as a service and evacuation tunnel and linked to the new structure by means of five cross-passages.

1 Introduction

The new Bözberg Tunnel with a total length of roughly 2.7 km is the longest single element among the structures on the 4-Metre Corridor, which were largely driven mechanically using a TBM. SBB-Infrastruktur for the first time invited tenders for the main project, the twin-track tunnel in keeping with the new “General Contractor Plus” award model and commissioned the Swiss contractor Implenia to implement it.

The project is located in the Canton of Aargau between Brugg and Frick and passes through the sophisticated geology of the Swiss Faltenjura. A particular challenge is posed by...

Related articles:

Issue 06/2015 Switzerland

New Bözberg Rail Tunnel: Start of Construction in Spring 2016

The Gotthard axis is to be extended to become a 4 metre corridor, so that in future semi-trailers with a corresponding 4-m corner height can also be transported. This will assist freight traffic...

more
Issue 01/2020

BIM Applications in Design and Construction of the Soft Ground Section at the Bözberg Tunnel

The Project The 4-m corridor of the SBB will enable all goods containers with a corner height of up to 4 m and a width of up to 2.6 m to be transported along the Gotthard axis from 2020. The new...

more
Issue 08/2017 Switzerland

Breakthrough at the Bözberg Tunnel

An important milestone for the 4 m corridor: On 29 November 2017, the tunnel boring machine broke through the last few metres of the Bözberg in Effingen. Due to the presence of unstable rock at the...

more
Issue 06/2017 Tunnels to Feuerbach and Bad Canstatt for the Stuttgart 21 Project

Injections to restrict ingressing Water in Rock containing Anhydrite

The water-bearing leaching front is sealed by means of drilling in advance of the excavation by grouting polyurethane so that no groundwater can come into contact with the anhydrite-bearing rock. For...

more
Issue 03/2017 Switzerland

Bözberg Tunnel-TBM should start drive in May

Swiss Railways (SBB) plan to provide a 4 m corridor along the entire Gotthard axis by 2020 in order to be able to transport semi-trailer (articulated) trucks with a height of 4 m by rail. For this...

more