Efficient Use of Forepoling Technology at the Arlinger Tunnel

The 1.35 km long Arlinger Tunnel is part of the first construction phase of the “Westtangente Pforzheim”, the connecting axis of the German federal roads 294 and 463 from the Black Forest to the motorway 8. After the completion of the Westtangente Pforzheim, the Arlinger Tunnel will contribute to a significant traffic relief of the city centre of Pforzheim.

The two-lane bi-directional tunnel with a cross-section of approximately 90 m², two breakdown bays, an operations centre, the rescue tunnel with a length of 1.1 km as well as four cross-passages were excavated for the most part using conventional tunnelling methods. The excavation work began in 2019 and was carried out using both drill and blast and excavator driving.

Pipe Umbrella with Squeezed Connection

Due to the highly variable ground conditions – clays, marl and limestone, shell limestone as well as karst cavities – the “AT – 139 Pipe Umbrella System” was used as a pre-support measure. For the fully mechanised installation, the two booms of the Epiroc “Boomer E2C” jumbo were equipped with the “AT – Pipe Umbrella Automation Unit”. For this, the squeezed connection of DSI Underground was used, which is characterised by the following main advantages:

Increased working safety

Improved load capacity

Optimised quality and utilisation

 

A squeezed connection consists of a prefabricated reduced male pipe end, which is force-fitted with its female counter piece using a hydraulic clamping cylinder.

In contrast to standard threaded connections, squeezed connections do not exhibit any significant weakening of the load-bearing capacity in the joint area. In the course of installing the approximately 10 km of pipe umbrella tubes, it also became clear that the use of the squeezed system made a significant contribution to the timely completion of the tunnelling work compared to conventional screw threads. Thanks to the fully mechanised installation, a new milestone was also set in terms of work safety in tunnelling.

SN anchors type SN20-180 and self-drilling bolts “DSI Hollow Bar System” type R32-250 were used for excavation support, and tubular spiles 38 x 4 mm and 42.5 x 3 mm were used for pre- support. The breakthrough took place in December 2020; the tunnelling work was completed successfully and on schedule.

x

Related articles:

Issue 06/2011 Croatia

AT-Pipe Umbrella Support System allows safe Driving of Omis Tunnel

The most important route between the Croatian seaports of Split and Makarska is the D8 National Road. This road was built very near to the shoreline of the Adriatic Sea in the 1960s. Today, the road...

more
Issue 04/2016 Germany

New Pforzheim Tunnel to be completed by 2025

The 903 m long Pforzheim rail tunnel, constructed from 1858 to 1860 between Ispringen and Pforzheim on the Pforzheim–Mühlacker line, most recently underwent refurbishing in 1984 and is now to be...

more
Issue 03/2020

Küssnacht Southern Bypass – Support Measures for a Shallow Soft Ground Tunnel Under a Built-Up Area

1 Introduction The first section of the southern bypass around the historic village centre of Küssnacht am Rigi in the Canton Schwyz is to be completed by September 2020. The objective is to relieve...

more
Issue 01/2019 Avesco | Sandvik

Dry Excavation with modified Tunnelling Jumbo

Description of Project Since 2014, a railway tunnel with two single-track tubes with lengths of 2449 and 2426 m has been under production starting from Stuttgart-Nord. The tunnel for its part is an...

more
Issue 01/2015 Germany

New Pforzheim Tunnel

In November 2014 the Deutsche Bahn launched measures for building a new rail tunnel between Ispringen and Pforzheim on the route between Karlsruhe and Mühlacker. The existing 903 m long tunnel was...

more