Switzerland

Breakthrough at Weinberg Tunnel in Zurich

The Weinberg Tunnel in Zurich, part of Swiss Federal Railways’ “Diameter Line Project”, was successfully broken through on 22nd November 2010. After boring a total of 4,382 m the convertible TBM resurfaced in the target shaft at the southern section of Zurich’s main train station.

From July to October 2008 the TBM was assembled on the main set-up area in the Brunnenhof shaft. From then until March 2010 it bored through the 4,105 m long hard rock section consisting of molasse rock. Between March 2010 and June 2010 the TBM was converted from hard rock mode to slurry shield mode.

In this set-up, it overcame the last 277 m to the target shaft. From a geological point of view, the transition from a tunnel face that is fully situated in molasse rock to a tunnel face that lies completely in soft ground below the ground water table was achieved on this section. Special support measures had been taken in advance along the soft ground section, i.e. a pipe umbrella support system had been built over a length of 120 m to 140 m in front of the target shaft.

The shield TBM with a bore diameter of 11.27 m was dismantled in January 2011, with the shield skin remaining in the ground in front of the target shaft.

The project that was commissioned by the Swiss Federal Railways SBB is being planned and supervised by the engineering consortium IG Zalo and carried out by the Joint Venture of Implenia Bau AG, Wayss & Freytag Ingenieurbau AG, Bilfinger Berger AG and PraderLosinger SA. Structural work after breakthrough will continue until mid 2012.

x

Related articles:

Issue 07/2012 Switzerland

Zurich Weinberg Tunnel: Installing the Rail Technology

Along with the underground through station – Löwenstraße – the roughly 4.8 km long, twin-track Weinberg Tunnel in Zurich forms the core of the SBB Zurich Cross Rail (DML) project, which connects...

more
Issue 05/2009 Switzerland

Zurich Weinberg Tunnel: All Drives forging ahead

The execution of the construction scheme involves 3 local main aspects: –?the main drive from the Brunnenhof installation yard –?undercutting the south section of Zurich Central Station...

more
Issue 05/2009 Construction Equipment

Mixing and Grouting Systems for the Weinberg Tunnel in Zurich/CH

Mixing and grouting systems made by Häny are being used to construct the new Alstetten – Zurich Main Station - Oerlikon cross-city underground link in Switzerland. In contract section 3 (Weinberg...

more
Issue 05/2010 Switzerland

Zurich cross-city Link: Weinberg Tunnel – Crossing the Limmat

The tunnel boring machine (TBM) used for producing the 2-track Weinberg Tunnel arrived at the for the time being final stopping point under the Zähringerstraße at the Central Station as scheduled...

more
Issue 08/2017

Eppenberg Tunnel: Convertible TBM for Rock and Soft Soil

The Eppenberg Tunnel with its connections to the existing track system is included in Lot A of the overall project. This project consists of the part-projects TP1 to TP3 and TP8, which are executed...

more