Switzerland

Repair Works in the Gotthard Base Tunnel

According to Swiss Federal Railways (SBB), the repair work on the Gotthard Base Tunnel is progressing as planned. SBB continues to expect the tunnel to be fully reopened in September 2024.

Since repair work began in October 2023, around seven kilometres of damaged rails have been replaced in the Gotthard Base Tunnel
Credit/Quelle: SBB CFF FFS

Since repair work began in October 2023, around seven kilometres of damaged rails have been replaced in the Gotthard Base Tunnel
Credit/Quelle: SBB CFF FFS
The installation of the new track change gate in the Faido multifunction station marks a significant step in the repair of the tunnel. Due to its size, the custom-built gate was brought into the tunnel in parts at the end of April 2024 and took around six weeks to assemble and install. In its final state, the track change gate will be around four metres wide and seven metres high. After installation, the electromechanical and hydraulic door control system will be installed in the track change gate and then tested.

Since the start of the reconstruction work at the end of October 2023, the carriageway has been completely renewed over seven kilometres. The rails have been replaced, as have over 20 000 sleeper blocks and the concrete layer in which they are embedded. At the Faido multifunction station, the two high-speed switches were also replaced along with the actuators.

Complete Recommissioning Scheduled for September 2024

Installation of the new track change gate in the Faido multifunction station
Credit/Quelle: SBB CFF FFS

Installation of the new track change gate in the Faido multifunction station
Credit/Quelle: SBB CFF FFS
The next steps include restoring the railway technology equipment, completing work on the tunnel installations – including the lighting and fire sensors – and testing and approving them. The tunnel will also be completely cleaned, including the cross-passages. For this purpose, the entire tunnel will be vacuumed with a special construction train and all the fine dust will be removed. Before the Gotthard Base Tunnel can be put back into full operation, extensive test and trial runs will be necessary. SBB still expects the Gotthard Base Tunnel to be fully reopened in September 2024.

x

Related articles:

Issue 03/2024 Switzerland | Schweiz

Repair Works in the Gotthard Base Tunnel

According to Swiss Federal Railways (SBB), the repair work on the Gotthard Base Tunnel is progressing as planned. SBB continues to expect the tunnel to be fully reopened in September 2024. The...

more
Issue 06/2023 Switzerland | Schweiz

Gotthard Base Tunnel: Serious Damage, Normal Operation Expected as of September 2024

The derailment of a cargo train in the Gotthard Base Tunnel on 10 August 2023 caused considerably more serious damage than initially assumed. The repair work will therefore take much longer than...

more
Switzerland

Gotthard Base Tunnel: Serious Damage, Normal Operation Expected as of September 2024

SBB has estimated that the tunnel will not be fully reopened for passenger and cargo trains until September 2024. From the timetable change on 10 December 2023, SBB intends to increase capacity for...

more
Issue 04/2024 Switzerland | Schweiz

Gotthard Base Tunnel Fully Operational Again

As of September 2, 2024, the Gotthard Base Tunnel is once again fully open to rail traffic. Almost 13 months after the derailment of a freight train on 10 August 2023, the world‘s longest railroad...

more
Switzerland

Gotthard Base Tunnel Fully Operational Again

The damage caused by the derailment of the freight train in the Gotthard Base Tunnel was serious. SBB currently estimates the amount of damage, including loss of earnings, at around 150 million swiss...

more