Switzerland

Gotthard Base Tunnel Fully Operational Again

As of September 2, 2024, the Gotthard Base Tunnel is once again fully open to rail traffic. Almost 13 months after the derailment of a freight train on 10 August 2023, the world's longest railroad tunnel (57 km) is now back to full capacity.

As of September 2, 2024, the Gotthard Base Tunnel is once again fully open to rail traffic
Credit/Quellet: SBB

As of September 2, 2024, the Gotthard Base Tunnel is once again fully open to rail traffic
Credit/Quellet: SBB
The damage caused by the derailment of the freight train in the Gotthard Base Tunnel was serious. SBB currently estimates the amount of damage, including loss of earnings, at around 150 million swiss francs. Around 140 million swiss francs thereof are likely to be insured. The estimation accuracy for both figures is +/- 20 percent.

Due to the extent of the damage, it took around one and a half months to clear the tunnel. During the repair work, around seven kilometers of the roadway had to be completely renewed, i.e. the rails were replaced, as were over 20 000 sleeper blocks and the concrete layer in which they are cast. In addition, the track change gate, two high-speed switches and many other safety and operationally relevant system components were replaced.

Risk Mitigation Measures at European Level and at SBB

According to the interim report of the Swiss Accident Investigation Board STSB, a broken wheel disk caused the derailment of the freight train in the Gotthard Base Tunnel. As freight transport is an international business, measures are needed at European level. In SBB's view, the recently published final report of the responsible task force (Joint Network Secretariat Taskforce Broken Wheel GBT) contains the necessary measures at European level to reduce the risk of further wheel breakages of a similar nature.

SBB is also implementing risk-mitigating measures in the short and medium term. In the short term, a maximum speed of 160 km/h applies in the area of the two portal lane changes in front of the Gotthard Base Tunnel in order to effectively reduce the impact of a similar, very unlikely event in this section. In the medium term, SBB is also planning to install trackside derailment detectors at the lane changes in and in front of the base tunnel and is examining the increased and optimized use of train control equipment.

x

Related articles:

Issue 04/2024 Switzerland | Schweiz

Gotthard Base Tunnel Fully Operational Again

As of September 2, 2024, the Gotthard Base Tunnel is once again fully open to rail traffic. Almost 13 months after the derailment of a freight train on 10 August 2023, the world‘s longest railroad...

more
Issue 06/2023 Switzerland | Schweiz

Gotthard Base Tunnel: Serious Damage, Normal Operation Expected as of September 2024

The derailment of a cargo train in the Gotthard Base Tunnel on 10 August 2023 caused considerably more serious damage than initially assumed. The repair work will therefore take much longer than...

more
Switzerland

Gotthard Base Tunnel: Serious Damage, Normal Operation Expected as of September 2024

SBB has estimated that the tunnel will not be fully reopened for passenger and cargo trains until September 2024. From the timetable change on 10 December 2023, SBB intends to increase capacity for...

more
Issue 03/2024 Switzerland | Schweiz

Repair Works in the Gotthard Base Tunnel

According to Swiss Federal Railways (SBB), the repair work on the Gotthard Base Tunnel is progressing as planned. SBB continues to expect the tunnel to be fully reopened in September 2024. The...

more
Switzerland

Gotthard Base Tunnel: Clearing and Rescue Operations Will Last Until End of September 2023

No Official Information Yet on Cause of Derailment and Extent of Damage The incident in the Gotthard Base Tunnel occurred in the early afternoon at the Faido multifunction station. The freight train...

more