Austria/Italy

Refinancing Applications Submitted for the Brenner Base Tunnel

Following a comprehensive analysis, BBT SE estimates the total project costs for the Brenner Base Tunnel at around 10.5 billion euros. After the cost forecast was approved by the supervisory board, the next step for the project company BBT SE was to apply for the necessary funding from the respective national funding agencies.

New Estimate of the Total Cost: 10.5 Billion Euros

The estimated total cost of the project is as follows:

The construction costs are forecast at 8.54 billion euros. This sum already includes the technical railway equipment (price basis of 1 January 2023).

The forecast costs for risks amount to 1.092 billion euros.

903 million euros are estimated for escalation, i.e. for the probable inflation of the future costs

The adjustment of the original total cost estimate of 9.6 billion euros according to the Austrian calculation method and 8.8 billion euros according to the Italian calculation method is mainly due to the development of inflation (e.g. price increases in the energy sector and for building materials).

The present total cost estimate was calculated on the basis of a joint (Austrian-Italian) inflation trend specifically for the BBT project; therefore, there is now only one joint cost estimate.

Project Funding

After the approval of the cost forecast, the next step for the project company BBT SE was to apply for the necessary funding from the respective national funding agencies: In Italy, the first steps were taken to obtain a new CIPESS (Comitato Interministeriale per la Programmazione Economica e lo Sviluppo Sostenibile) decision. In Austria, the new data has already been sent to the ÖBB, which will take it into account when drawing up the new framework plan.

EU Funding Continues

The funding agencies of the European Commission have again promised their strategic and financial support until the completion of the infrastructure project.

To cover the costs already incurred, Italy and Austria will receive co-financing from the European Union of 50% for the planning and exploration work and 40% for the construction measures. So far, the EU has pledged co-financing totalling around 1.6 billion euros.

Under the new CEF 2021–2027 programme, BBT SE is participating in a tender for European co-financing to obtain co-financing for costs from 1 July 2023. A result is expected in summer 2023.

x

Related articles:

Italy/Austria

EU Pledges a Further 700 Million Euros in Funding to Brenner Base Tunnel

The Trans-European Transport Networks (TEN-T) are the priority projects of the European Union for the large-scale expansion of European infrastructure. The Brenner Base Tunnel is considered a European...

more
Issue 02/2021 Austria

Brenner Base Tunnel Project Provides Data for Flooding Forecast Models

On World Water Day 2021, which takes place every year on 22 March, the Brenner Base Tunnel Society (BBT SE) drew attention to a positive effect of the construction works. The insights collected...

more
Issue 01/2022 Austria

Brenner Base Tunnel: Tender Launched for Pfons–Brenner Construction Lot

If the tendering process goes according to plan, the Pfons–Brenner construction lot is expected to be awarded within 2022. The construction period for the services to be carried out is estimated at...

more
Issue 07/2011 Austria/Italy

Brenner Base Tunnel: Main Phase started

Phase III, the main construction phase of the Brenner Base Tunnel (BBT), currently the European Union’s /EU’s) most important transport infrastructural project, was started on April 18, 2011 in...

more
Issue 02/2011

Brenner Base Tunnel: Project status

1 Basic concept The Brenner Base Tunnel is a nearly horizontal rail tunnel with 2 parallel tubes. The tunnel runs for 55 km between the railway stations of Innsbruck and Fortezza and is connected...

more