Stuttgart 21:Transport of 8 Million Tonnes of Spoil

“Half of our job is done now and the end of the transport is foreseeable“, stated Wolf-Dieter Tigges, manager of the central construction logistics (ZBL) on the DB project Stuttgart–Ulm. His department has been responsible since June 2014 for the carting away of material produced by the inner-city construction sites of the future rail node in Stuttgart. On 24 April 2017, the 4000th train departed from the handling area of the construction logistics department at the north station – meaning that four of the eight million tonnes of earth and rock have now been transported away from the sites of the main station and adjacent tunnels.

40 Million Tonnes of Spoil on the Overall Project

Altogether about 20 million tonnes will be produced by the part project Stuttgart 21. The eight million tonnes to be transported through the central construction logistics department come from the project sections 1.1 (Valley crossing with main station), 1.2 (Filder Tunnel), 1.5 (Feeders to Feuerbach and Bad Cannstatt with S-Bahn urban transit) und 1.6a (Feeders to Ober- and Untertürkheim). In addition, about twelve million tonnes of spoil are disposed of directly by the contractors for the currently decentralised logistics areas of Filder and...

Related articles:

Germany

Stuttgart 21: Transport of 8 Million Tonnes of Spoil

40 Million Tonnes of Spoil on the Overall Project Altogether about 20 million tonnes will be produced by the part project Stuttgart 21. The eight million tonnes to be transported through the central...

more
Issue 06/2016 Germany

One Third of the Tunnels of Stuttgart 21 driven

The DB Projekt Stuttgart–Ulm GmbH passed the 20 km mark for tunnelling on the Stuttgart 21 project at the end of September 2016, meaning that more than a third of the tunnels for the reorganisation...

more
Germany

Stuttgart 21: Breakthrough of the Last Tunnel to the Main Station

The tunnel makes the connection between the future main station and the airport particularly fast: today, the connection takes just under half an hour; in the future, the journey time will be only...

more
Issue 03/2020 Germany

Stuttgart 21: Breakthrough of the Last Tunnel to the Main Station

At the beginning of May 2020, German Railways (DB) reached another milestone in the Stuttgart 21 project: With the breakthrough of the eastern tube of the 9.5 km long Filder Tunnel, the last of four...

more
Issue 05/2020 Germany | Deutschland

Stuttgart 21: Project Partners Celebrate the Start of Tunnelling for the Airport Traffic Hub

Deutsche Bahn (German Railways) is taking the next important step in the course of Stuttgart 21 at Stuttgart Airport. On 20 July 2020, the project partners celebrated the start of the main...

more