Stuttgart 21: Breakthrough of the Last Tunnel to the Main Station

At the beginning of May 2020, German Railways (DB) reached another milestone in the Stuttgart 21 project: With the breakthrough of the eastern tube of the 9.5 km long Filder Tunnel, the last of four tunnels has arrived at the future Stuttgart main station. The connection between the Filder plain in the south of Stuttgart and the Stuttgart basin is now complete.

The tunnel makes the connection between the future main station and the airport particularly fast: today, the connection takes just under half an hour; in the future, the journey time will be only eight minutes.
Roland Pofalla, Member of the DB Board of Management responsible for Infrastructure, “This is a milestone on the way to the new Stuttgart rail junction. My thanks go to all those involved who managed this tunnel breakthrough on schedule despite the difficult conditions of the Corona crisis.”
 “Of course, it is unusual not to be able to celebrate the success of a tunnel breakthrough together with all those involved on site. The highest respect goes to to our miners and engineers who, with extraordinary prudence, have brought the tunnelling work to a successful conclusion in recent weeks,” said Andreas Rath, Managing Director of the JV ATCOST 21.

In the Stuttgart 21 project, a total of 50 of 59 km of tunnels, or 85%, have now been driven.

x

Related articles:

Issue 03/2020 Germany

Stuttgart 21: Breakthrough of the Last Tunnel to the Main Station

At the beginning of May 2020, German Railways (DB) reached another milestone in the Stuttgart 21 project: With the breakthrough of the eastern tube of the 9.5 km long Filder Tunnel, the last of four...

more
Issue 06/2017 Germany

Breakthrough in Filder Tunnel

The 9.5 km long Filder Tunnel connects Stuttgart Central Station, lying in a valley basin, with the Filder plateau located some 155 m higher. The four sections of its two tunnel tubes are being driven...

more
Issue 06/2019 Germany | Deutschland

Stuttgart 21: First Tube of the Untertürkheim Tunnel Broken Through

The Deutsche Bahn has reached another important milestone on the Stuttgart 21 project: in the middle of November 2019, after about two years of excavating the Untertürkheim Tunnel, the first of two...

more
Issue 06/2016 Germany

One Third of the Tunnels of Stuttgart 21 driven

The DB Projekt Stuttgart–Ulm GmbH passed the 20 km mark for tunnelling on the Stuttgart 21 project at the end of September 2016, meaning that more than a third of the tunnels for the reorganisation...

more
Issue 05/2023 Germany

Stuttgart 21: Breakthrough at the Airport Tunnel – All Tunnels Completed

Deutsche Bahn has successfully driven all tunnels of the Stuttgart 21 project. In total, the tunnellers have dug around 56 kilometres of tunnel. With the last tunnel breakthrough on 14 September 2023...