Switzerland

Redeveloping the Axen Route with 9 Tunnels to begin in 2017

The SBB is using the time between the opening of the Gotthard and the Ceneri Base Tunnels to upgrade and renew the access routes to the tunnels. This also includes the Axen route, where the track nearest the lake is to be redeveloped and upgraded. Preliminary operations started there in early October 2016. The two-way route between Brunnen and Flüelen forms an important access to the GBT. In order to ensure that the route is suitable for long-term use, the SBB was compelled to plan to renew the track nearest the lake prior to 2030; the track at the mountain side had already been comprehensively renovated in 2008/2009.

The renovation process as such for the Axen route will commence in January 2017 in three stages and is due to be completed in December 2019. Within the scope of the project, the SBB will redevelop a total of nine tunnels with an overall length of almost 6 km. Towards this end, the existing engineering structures (portals, arches, abutments and drainage systems) as well as the entire rail technology with track, cable systems and overhead wire are to be renewed. In the two longest tunnels, the self-rescue facilities will be expanded and updated. The Morschach Tunnel has been modified to cope with containers with up to 4 m corner height since the summer of 2016. This will mean that the entire Axen route will be suitable for transporting 4 m high loads. The total project is estimated to cost around 120 million Swiss francs. Once redeveloped, the Axen route will be able to fulfil its purpose for rail operations up until 2070.

x

Related articles:

Issue 07/2016 Switzerland

Redeveloping the Axen Route with 9 Tunnels to begin in 2017

The SBB is using the time between the opening of the Gotthard and the Ceneri Base Tunnels to upgrade and renew the access routes to the tunnels. This also includes the Axen route, where the track...

more
Issue 01/2015 Switzerland

SBB awards Contract to build the Eppenberg Tunnel

The SBB (Swiss Federal Railways) awarded the main contract section for the four-track upgrading of the Olten–Aarau route in November 2014. The contract worth some 274 million Swiss francs was awarded...

more
Issue 03/2024

SBB Dual-Track Tunnel Ligerz: Eliminating a Traffic Bottleneck With Complex Boundary Conditions

1 Introduction The SBB’s southern ridge-base line (Jurasüdfußlinie) runs from Geneva/Lausanne via Neuchâtel and Biel to Basel/Zurich. The cur- rent single-track line in the Ligerz–Twann section...

more
Switzerland

Major Rehabilitation Works at the Hauenstein Base Tunnel

In addition, four tunnel-wide single-track closures are planned. They will take place in 2024, 2026, 2027 and 2028, each during five weeks in the summer holiday period, when there is less traffic....

more
Issue 05/2023 Switzerland

Major Rehabilitation Works at the Hauenstein Base Tunnel

In addition, four tunnel-wide single-track closures are planned. They will take place in 2024, 2026, 2027 and 2028, each during five weeks in the summer holiday period, when there is less traffic....

more