Switzerland

Breakthrough at the Bözberg Tunnel

An important milestone for the 4 m corridor: On 29 November 2017, the tunnel boring machine broke through the last few metres of the Bözberg in Effingen. Due to the presence of unstable rock at the portal, there had been a danger of rockfall or slope sliding, Therefore Swiss Railways (SBB) took special safety precautions for the breakthrough at the portal as the existing main line runs very near the new tunnel portal in Effingen. This was protected with a temporary rolled-out protection wall. During the breakthrough, the slope was continuously monitored with measuring instruments. An emergency arrangement was also set up in order that the main line could be closed immediately if the scree started sliding. The tunnelling specialists prepared an additional pipe screen that also prevented a withdrawal of the tunnel boring machine in order to make the portal safe for the official breakthrough ceremony with invited guests on 13 December 2017.

By 2020, SBB intends the implementation of a 4 m corridor on the entire Gotthard axis in order to be able to transport semitrailers with a height of 4 m by rail. The new Bözberg Tunnels is the most important individual project with an investment volume of about 350 million Swiss francs. A new two track tunnel almost 2.7 km long will be completed by 2020 parallel to the existing two-track Bözberg Tunnel. After the opening of the new tunnel, the old tunnel will be rebuilt for two years as a service and escape tunnel connected to the new tunnel with five cross passages.

x

Related articles:

Issue 03/2017 Switzerland

Bözberg Tunnel-TBM should start drive in May

Swiss Railways (SBB) plan to provide a 4 m corridor along the entire Gotthard axis by 2020 in order to be able to transport semi-trailer (articulated) trucks with a height of 4 m by rail. For this...

more
Issue 06/2015 Switzerland

New Bözberg Rail Tunnel: Start of Construction in Spring 2016

The Gotthard axis is to be extended to become a 4 metre corridor, so that in future semi-trailers with a corresponding 4-m corner height can also be transported. This will assist freight traffic...

more
Issue 01/2020

BIM Applications in Design and Construction of the Soft Ground Section at the Bözberg Tunnel

The Project The 4-m corridor of the SBB will enable all goods containers with a corner height of up to 4 m and a width of up to 2.6 m to be transported along the Gotthard axis from 2020. The new...

more
Issue 02/2018

New Bözberg Tunnel: Structural Measures when Tunnelling in squeezing Rock

1 Introduction The new Bözberg Tunnel with a total length of roughly 2.7 km is the longest single element among the structures on the 4-Metre Corridor, which were largely driven mechanically using a...

more
Issue 02/2014 Germany

Scheibengipfel Tunnel – Breakthrough at the South Portal

The breakthrough of the Scheibengipfel Tunnel for the Reutlingen bypass has been accomplished. On January 27, 2014 a Max Bögl excavator broke through the last partition wall at the south portal with...

more