Final Double Breakthrough at the Emscher Sewer

With the breakthrough of the last two tunnel boring machines into the target pit of construction section 40 on June 12, 2017 the tunnel and pipe jacking work for the Emscher sewer has been completed.

Over a period of 25 years numerous Herrenknecht tunnelling machines were used in the Europe-wide unique environmental and sewage project of Emschergenossenschaft. Between October 2014 and June 2017 the two EPB Shields (Ø 3397 mm) used by construction company Porr built the two 10 km long main collectors with the support of Herrenknecht service experts. The site crews were able to keep the average machine availability above 95 % over the entire tunnelling period.

Compact Tunnelling System

The two EPB Shields were the only machines in the entire project using the segmental lining method. With an inside diameter of 2.6 m, the twin tubes of construction section 40 are among the smallest segmentally lined tunnels in the world. The entire tunnelling system with a length of around 85 m was designed to be accordingly compact. The logistics were also adapted for the small diameter. Thus, for example, a muck removal concept with a locomotive was used, where excavated material was transported in buckets to the shaft and the finished segments were transported to the tunnel face.

Technically demanding Tunnel Alignment

One of the special tasks in the realization of construction section 40 was the technically demanding tunnel alignment with several partially tight curve radii of up to 200 m. The alignment runs mostly below the A2 motorway and a multitude of inner city supply lines. In addition, an approximately 300 m long geological fault zone with sandy and groundwater-bearing subsoil had to be passed through. The limited space available at the total of three launch shafts necessitated a well-thought-out logistics concept.

Emscher Conversion has been running for 25 Years

Work on the overall Emscher conversion project began back in 1992, covering more than 400 km of new underground sewer tunnels. The inhomogeneous ground, the pipe position in up to 40 m depth, the long pipe jacking distances, the partially complex logistics and the wide range of different construction situations posed particular challenges in the creation of the necessary tunnel structures. Over almost 25 years and 60 km of the main and secondary sections the contractors relied on Herrenknecht‘s project-specific tunnelling technology for the underground excavation work in construction sections 20, 30 and 40. This included numerous AVN machines for pipe jacking in the smaller diameter range, EPB Shields using the pipe jacking and segmental lining methods as well as a Vertical Shaft Sinking Machine or VSM to sink a 23 m deep launch shaft. In individual construction phases, Herrenknecht Group partners supported the construction process. VMT supplied TBM navigation systems as well as various communication, data management and safety systems (also see the article in the next issue, tunnel 7/2017). Herrenknecht Formwork produced segment moulds and MSD supplied rolling stock, a lifting beam and a tilting table for the pipe plant in Gelsenkirchen.

Commissioning of the Emscher Sewer planned for 2020

The Emscher, whose source rises in Holzwickede to the east of Dortmund, passes through a series of cities in the German Ruhr area on its 80 km path before it flows into the Rhine. Since the beginning of industrialization around 1850, the small lowland river was used as an open channel for sewage, flood and rainwater and degenerated into the dirtiest river in Europe. With the renaturation of the stream, one of the main tasks of the Emschergenossenschaft founded in 1899, in future sewage and rainwater will be separated again, drained away underground and purified in intermediate treatment plants. As a result the river will become clean again in the long term. Commissioning of the 51 km long Emscher sewer is planned for the end of 2020.

x

Related articles:

Issue 05/2014 Long Jacking Sections

Pipe Jacking for the Emscher Interceptor attains Section Lengths in Excess of 1100 m

Converting the Emscher and planning the Emscher Interceptor The 85-km long River Emscher flows right through the Ruhr District. It has its source to the east of Dortmund and flows into the Rhine near...

more
Issue 07/2017 Germany

New Emscher Sewer Tunnel: VMT provided TBM Navigation and Work Safety Concept in BA 40

The construction of the 51 km long Abwasserkanal Emscher (AKE) sewer tunnel is the largest individual project to improve the River Emscher in the Ruhr, Germany and is technically and financially one...

more
Issue 02/2018

Emscher Interceptor: Special geotechnical Tunnelling Features in Section 40

1 Introduction The Emscher Interceptor AKE (Fig. 1) has an internal diameter of 1.6 m to 2.8 m and is being constructed at depths of up to 40 m. Both pipe jacking and tunnel boring machines were...

more
Issue 06/2023 Singapore | Singapur

Tunnelling for Deep Tunnel Sewerage System Completed

A milestone for the major Deep Tunnel Sewerage System (DTSS) project in Singapore: the five contractors have completed tunnelling works for the second construction phase of the gigantic sewer pipe...

more
Singapore

Singapore: Tunnelling for Deep Tunnel Sewerage System Completed

A total of 19 Herrenknecht Tunnel Boring Machines (TBMs) had excavated and lined some 49 km of tunnel since 2019. In addition, a Vertical Shaft Sinking Machine (VSM) was used. Marking the completion...

more