Crossrail: Mega Infrastructure Project taking Shape

The first five tunnel drives for the altogether eight bores for the giant Crossrail infrastructure project have begun in the heart of the Olympic City of London. The construction of the underground stations is also progressing. The following report provides an overview of the western tunnel section (C300) as well as the construction of two stations (C410).

Chris Dulake, BSc, C.Eng, FICE, Chief Engineer, Crossrail/UK; Dipl.-Ing. Sascha Boxheimer, Wayss & Freytag Ingenieurbau AG, Tunneling Division, Frankfurt am Main/Germany

Related articles:

Issue 02/2013

Crossrail: Mega Infrastructure Project taking Shape

The Crossrail project in London is a part of the roughly 118 km long regional line between Maidenhead and Heathrow in the west and Shenfield and Abbey Wood in the east. The line will serve a total of...

more
Issue 08/2015

Crossrail: “TBM First” Strategy for Lot C300/410 and permanent Shotcrete Lining Support

Project Overview The BFK joint venture (BAM Nuttall – Ferrovial – Kier) was commissioned to undertake the Crossrail C300/410 project in mid-2010 using a special proposal. This section, shown in blue...

more
Issue 04/2015 United Kingdom

Mission accomplished: Crossrail Tunnelling concludes

With the breakthrough of Crossrail’s tunnel boring machine Victoria at Farringdon Station on May 23 at 5.30 am, London has made tunnelling history: Victoria is the last of eight Herrenknecht TBMs...

more
Issue 06/2013 Book Review

DBV Conference 2013

Strengthen the Infrastructure – Secure the Future! April 11 + 12, 2013 in Hamburg Published by: German Society for Concrete and Construction Technology Inc. (DBV) 2013, Volume 23, 168 pp. with 250...

more
Issue 03/2014 United Kingdom

Simon Wright appointed as new Crossrail Programme Director

At the end of April Crossrail announced that Simon Wright has been appointed as new Programme Director. Simon Wright, currently Project Development Director at Network Rail, and previously Director of...