Marienhof in Munich: Level E-5 Steel Bracing and Compensation Grouting Trial Area

Construction of the Marienhof station continues at a fast pace. The construction of the diaphragm walls, primary supports and the roof deck had already been completed by the time the JV Marienhof was presented in tunnel 4/2022. The overall project was outlined in detail in tunnel 2/2023 and an overview of the status of the work was given in tunnel 5/2023. The following article deals with specific sections of Germany‘s deepest S-Bahn station in Munich.

Since the start of construction in September 2019, the excavation support with 54 m deep diaphragm walls, the 68 m deep primary supports for transferring the loads of the deck slabs during the construction period, the roof deck (level E0) and the various intermediate levels down to and including excavation level E-4 have been constructed. Work is currently (summer 2024) underway at level E-5 .

1 Current Construction Activities

In May 2024, level E-4 with the temporary supply openings was concreted. In June 2024, the excavation of level E-5 was started through these openings up to approx. 25 cm...

Related articles:

Issue 05/2023

Marienhof in Munich: Construction Work on the Access Structure in Full Swing

Since the start of construction in September 2019, the securing of the excavation by the diaphragm walls, the 50 primary supports for transferring the loads of the deck slabs during construction and...

more

Marienhof in Munich: Construction of Germany’s Deepest S-Bahn Station Is Underway

Around 6 million people live in the Munich region, 1.5 million of them in the city itself. With an increase in employment of around 23 % over the last ten years, the southern German metropolis is...

more
Issue 05/2023

2nd Munich S-Bahn Main Line: Tender for the Eastern Section Until the End of 2023

Starting at Marienhof, award unit 733 (VE 733, Fig. 1) comprises the construction of the two traffic tunnel tubes with cross passages and intermediate exploration and rescue tunnel (ERS), rescue...

more
Issue 05/2023

Munich 2nd Main Line – Marienhof Station

Excavation Proceeded to a Depth of 23 m Work on the new Marienhof station on the 2nd Munich main line is progressing. The excavation for the station‘s central access structure in the heart of...

more
Issue 05/2023

Tunnel Construction West and Main Station in Munich: Current Status of Ongoing Works

The lot of award unit 30 (VE 30) starts in the west after Laim Station with the starting shaft for the TBM in front of the Donnersberger Bridge and ends with tunnel construction at the Marienhof...

more