Turkey | Türkei

Final TBM Breakthrough at Bahçe–Nurdağı Railway

In June ‘23, a 8.0 m diameter Robbins Single Shield TBM completed its second tunnel at Turkey’s Bahçe–Nurdagˇi Railway
Credit/Quelle: Robbins

In June ‘23, a 8.0 m diameter Robbins Single Shield TBM completed its second tunnel at Turkey’s Bahçe–Nurdagˇi Railway
Credit/Quelle: Robbins
In June 2023, a 8.0 m diameter Robbins Single Shield TBM completed its second tunnel at Turkey’s Bahçe-­Nurdağı Railway. The machine completed 9.6 km of tunneling, adding on to the 9.2 km it completed in its initial railway tunnel in 2020 – for a total of more than 18 km bored.

Geology in the second tunnel was comparable to the first, including incredibly hard and abrasive metasandstone with quartz, with an average of 220 MPa UCS and a Cerchar abrasion value of 3.87. The rock has some of the most extreme hardness and abrasiveness ever measured in Turkey.

After its first bore in the difficult ground, the machine required some inspection and repairs. “The biggest repairs we undertook with Robbins Field Service technicians were the main bearing seal change and checking and repairing of the TBM before launching it on the twin tunnel after the completion of the first tunnel. Both operations were completed in a short time due to good planning with Robbins technicians,” said Deniz Şahin, TBM Chief for contractor İntekar Yapı.

The machine began its second bore in February 2021, achieving a best monthly advance rate of 411 m. “During tunneling we performed a normal maintenance program as given in the TBM manual, and the machine had minimum downtime,” said Şahin.

The twin rail tunnels, for owner Turkish State Railways Directorate (TCDD), will provide an economic boost to a region recovering from two consecutively devastating earthquakes with magnitudes of 7.8 and 7.6 that occurred in February 2023. The project site is located very close to the intersection of two large active fault zones, the East Anatolian Fault (EAF) and Dead Sea Fault (DSF).  The tunnels were inspected after the event and were found to have sustained only minor cracking in a few segments. The new rail line will provide service between the towns of Bahçe and Nurdağı and is part of the TCDD’s plan to overhaul the railway connection in southeastern Turkey by providing a shorter, faster route in one of the country’s busiest railway corridors.

x

Related articles:

Issue 05/2020 Turkey

Bahçe–Nurdagı Railway Project: First TBM-Drive Successfully Completed

The Turkish State Railways Directorate (TCDD) is aiming to overhaul the railway connection in southeastern Turkey by providing a shorter, faster route in one of the country’s busiest railway...

more
Issue 04/2018

Turkey’s hardest Rock: The Bahce–Nurdag High Speed Railway Tunnel

Contractor Intekar Yapi Turizm Elektrik Insaat San. ve Tic. Ltd. Sti chose a Robbins Single Shield TBM, 8 m in diameter (Fig. 1), to excavate one section of tunnel. Mixed ground conditions prevail on...

more
Issue 02/2021 China

China’s Largest Robbins Crossover TBM Launches on Pearl River Delta Intercity Railway

The largest ever Robbins Crossover (XRE) TBM in China launched in late March 2021 in Guangzhou for contractors Sichuan Jinshi Heavy Equipment Leasing Co., Ltd and CREC Bureau 2. The 9.16 m diameter...

more
Issue 02/2019 Turkey

TBM-Excavation of Turkey’s longest Water Tunnel

Excavation of Turkey’s longest water tunnel came to an end in December 2018. To get there, a 5.56 m diameter Robbins Crossover (XRE) TBM and the contractor JV of Kolin/Limak had to overcome dozens of...

more
Issue 07/2015

Turkey’s tough Geology: The Genesis of today’s Crossover TBMs at Kargı

The K?z?l?rmak – Turkish for “Red River” – is the longest river in Turkey. The project includes a 13 m high, 450 m wide earth dam with a concrete spillway in the southern end and a water intake...

more