Turkey

TBM-Excavation of Turkey’s longest Water Tunnel

Excavation of Turkey’s longest water tunnel came to an end in December 2018. To get there, a 5.56 m diameter Robbins Crossover (XRE) TBM and the contractor JV of Kolin/Limak had to overcome dozens of major fault zones and water pressures up to 26 bar. After the breakthrough the completed na­tional priority water line was scheduled to go into operation in March 2019.

The 31.6 km long Gerede Water Transmission Tunnel is an urgently needed project due to severe and chronic droughts in the capital city Ankara. Its final leg, a 9.0 km section of extremely difficult ground including sandstone agglomerate, limestone and tuff, was just one section in the middle of a tunnel widely considered to be the most challenging ever driven by TBMs in Turkey. The Kolin/Limak JV called in the Robbins XRE Dual-Mode TBM to complete the tunnel, which was at a standstill. The three Double Shield TBMs that had been excavating the tunnel had encountered incredibly difficult geology including massive inrushes of mud and water.

The Crossover machine was assembled underground in spring 2016 and began boring in summer. Within the first 50 m of boring it had successfully passed through the section that buried the original Double Shield TBM. The machine was required to be used in EPB mode as it encountered water pressures up to 26 bars, alluvium, flowing materials, clay and a total of 48 fault zones. Together with the difficult geological conditions the travel time to reach the TBM within the tunnel had effects on TBM performance. Despite this constraint, the tunnel excavation achieved a best day of 29.4 m, best week of 134.6 m and a best month of 484 m.

x

Related articles:

Issue 02/2021 China

China’s Largest Robbins Crossover TBM Launches on Pearl River Delta Intercity Railway

The largest ever Robbins Crossover (XRE) TBM in China launched in late March 2021 in Guangzhou for contractors Sichuan Jinshi Heavy Equipment Leasing Co., Ltd and CREC Bureau 2. The 9.16 m diameter...

more
Issue 07/2015

Turkey’s tough Geology: The Genesis of today’s Crossover TBMs at Kargı

The K?z?l?rmak – Turkish for “Red River” – is the longest river in Turkey. The project includes a 13 m high, 450 m wide earth dam with a concrete spillway in the southern end and a water intake...

more
Issue 03/2016 Mexiko

Túnel Emisor Poniente II – Mechanized Excavation

The Valley of Mexico consists of a drained clay lake bed interspersed with volcanic rock and boulders from long dormant, buried volcanoes. Chronic groundwater depletion has resulted in soils that sink...

more
Issue 03/2017

High-Stakes Headrace

The JV contractor responsible for the headrace tunnel, Limak/AGE, opted for a unique type of TBM to bore in ophiolite, flysch, mélange and breccia with suspected water inflows up to 20 bar. The 6.2 m...

more
Issue 03/2011

Double Shield TBM for Indian Water Tunnel

Project Background Eastern areas of India’s Andhra Pradesh state receive only 20 cm of rainfall per year - an amount comparable to Africa’s Kalahari Desert. The Andhra Pradesh Irrigation Department...

more