Austria

Brenner Base Tunnel: Transport and Assembly of TBMs Wilma and Olga

The most important components of the TBM “Wilma” arrived at the “H53 Pfons–Brenner” construction lot of the Brenner Base Tunnel in mid-April 2024: The main drive and the gearbox housing were delivered to the construction site in Wolf/Steinach am Brenner on a special transport.

The double-shield TBM “Wilma” has a bore diameter of 10.37 metres and a total weight of 2700 tonnes. The length is approx. 180 metres. The tunnel boring machine consists of around 80 000 individual parts, which require up to 170 lorry loads to transport. The cutterhead and the main drive form the centrepiece of a TBM – these parts alone weigh around 264 tonnes and are up to 6.6 metres wide.

TBM Wilma starts in autumn 2024

After a three-month installation period in the assembly cavern, “Wilma” will begin its drive towards Innsbruck in autumn. The TBM will cover around 7.5 tunnelling kilometres on its way. At the end of April, transport of the twin TBM “Olga” from the Herrenknecht factory in Schwanau, Germany, to Steinach also began.

Transport of the TBM drive from the Pfons-Brenner construction site via the access tunnel to the assembly cavern using self-propelled industrial rollers. A high level of experience is required of the drivers, who guide the transport at walking speed
Credit/Quelle: BBT SE/Hetfleisch

Transport of the TBM drive from the Pfons-Brenner construction site via the access tunnel to the assembly cavern using self-propelled industrial rollers. A high level of experience is required of the drivers, who guide the transport at walking speed
Credit/Quelle: BBT SE/Hetfleisch

Tunnel Boring Machines on the Move: Challenges on the Heavy Haulage Route

Due to construction sites in the Stuttgart area and the Arlberg Tunnel closure, the special transports from Germany for the main drive could not take the shortest route. Depending on the dimensions and weight, a diversion of around 700 kilometres had to be accepted.

Due to the high transport load, various bridge structures in Germany and Austria had to be checked in advance by structural engineers for their load-bearing capacity. This resulted in special requirements, such as a precise specification of the driving lane over the bridge, solo driving and walking speed.

For some transports, traffic signs even have to be dismantled and parking or stopping bans put in place. Additional carriageway slabs are laid out in particularly narrow places. Preparations for the delivery of the TBM parts began in mid-2023. This long preparation time is needed to plan and coordinate the road transport, the delivery into the tunnel with the self-propelled vehicles and mobile cranes and the assembly in the cavern.

x

Related articles:

Austria

Final TBMs of the Brenner Base Tunnel Have Been Launched

A Total of Nine TBMs Excavate the Brenner Base Tunnel The TBMs Wilma and Olga are the last two of the nine tunnel boring machines to be used in the construction of the Brenner Base Tunnel. After...

more
Issue 05/2024 Austria

Final TBMs of the Brenner Base Tunnel Have Been Launched

The launch of the last two tunnel boring machines of the Brenner Base Tunnel was celebrated with a ceremony on 18 September. “Wilma” and “Olga” will drive the two main northbound tunnels in the...

more
Issue 05/2024

Breakthrough and Launch Ceremony at the Brenner Base Tunnel

Of the tunnel system, which is over 220 km long in total, 180 km have currently been driven – 80 km of which are main tunnels, 56 km exploratory tunnels and 44 km access, rescue and logistics...

more

TBM “Lilia” Started Excavation at the Brenner Base Tunnel

On this day, the first segment ring, consisting of six segments, was also installed. The TBM “Lilia” has an excavation diameter of about 10.4 m and a length of about 160 m, including the back-up...

more
Issue 02/2023 Austria/Italy

Brenner Base Tunnel: TBM Virginia Has Reached the Brenner

After 4 years, the first tunnel boring machine (TBM) of a main tunnel in the Brenner Base Tunnel successfully completed driving on 30 March 2023. TBM Virginia covered around 14 km on its journey,...

more