Jagdberg Tunnel on the A4 Motorway

Jagdberg Tunnel on
the A4 Motorway
Eisenach–Görlitz

Untertiteltext Englisch

A report on the start of construction on the Jagdberg Tunnel in Thuringia was provided at length in tunnel 1/2009 p. 8 ff. The following article follows on from presenting the project launch and concentrates on excavating the tunnel, the geology and the effects of the drive that was undertaken.

1 Introduction

The moment had arrived on August 27, 2009. Practically almost 9 months after work officially began on the tunnel on September 26, 2008, the official breakthrough of the first of the 2 roughly 3,100 m long tunnel bores, the southern bore, was ceremoniously celebrated. A week later on September 3, 2009 the northern bore followed. As a result contrary to all forecasts the crown drives for the southern and northern bores were completed some 9 months earlier than predicted (Fig. 1).

Both bores were driven with a slight time gap by drill+blast with an advancing crown in a continuous...

Related articles:

Issue 03/2010 Jagdberg Tunnel on the A4 Motorway

Jagdberg Tunnel on the A4 Motorway Eisenach–Görlitz

1 Introduction The moment had arrived on August 27, 2009. Practically almost 9 months after work officially began on the tunnel on September 26, 2008, the official breakthrough of the first of the 2...

more
Issue 04/2015

Ceneri Base Tunnel: Current Construction Status and Prospects

1 Description of the Project By creating the first virtually level rail route through the Alps, the NRLA opens up exciting new perspectives for rail transport. Freight can then be transported...

more
Issue 01/2013

Brenner Base Tunnel: Importance of Preliminary Prospection

1 Introduction Preliminary geological prospection and constant prospection during construction are of fundamental importance for proper excavation. Using the example of the Brenner Base Tunnel, this...

more
Issue 07/2010 Switzerland

Gotthard Base Tunnel: TBM restarts in Faido west tunnel

On 4 March 2010 excavation had to be stopped in the west tunnel of the Gotthard Base Tunnel some 9 km from the Faido multifunction station due to a rock inrush, and exploratory bores had to be...

more
Issue 01/2010 Austria

Brenner Base Tunnel: Stage reached by Construction

1?The TEN Axis from Berlin to Palermo The trans-border European priority scheme TEN Project No. 1 represents a roughly 2,200 km long high-speed railway route between Berlin/D and Palermo/I. Between...

more