Germany

TBM at the Boßler Tunnel starts Drive and Ring Construction

The TBM named “Kätchchen” used to drive the Boßler Tunnel began its work in mid-April, 2015. The machine built by Herrenknecht first tackled the eastern bore, which will one day accommodate the track running from Ulm to Stuttgart. It advanced from the start-up section at the Aichelberg portal up the Alb towards the access tunnel already produced at Umpfental near Gruibingen.

Mathias Breidenstein, the project manager of the DB Projekt Stuttgart–Ulm GmbH for the Alb ascent section on the new Wendlingen-Ulm rail route commented: “the engineers at the Boßler Tunnel have worked a long time for this day. We are delighted that the cutting wheel with 11.39 m diameter propelled by almost 6200 HP is now continuously eating away at the rock thus advancing the approx. 2480 t heavy and 110 m
long TBM. During the first two months the tunnellers get used to the rock and the machine. In this phase we make less progress prior to increasing the rate of advance to try to accomplish some 500 tunnel metres per month”. Essential measurements on the surface accompanied the start of excavation. The pedestrian and cycling path immediately in the vicinity of the TBM start-up zone had to be closed while the measurements were carried out. I

TBM is applied for a longer Distance

During recent months the railways and the contractor have concentrated on optimizing the Boßler Tunnel construction scheme. Intensive investigations of the geological conditions for the 8806 m
long tunnel revealed that the geology permitted the TBM to be applied for a substantially longer distance. Previously it was intended to use mechanized means over a length of some 2.8 km per tunnel tube. “Now we are planning to excavate around 7500 m in the eastern bore, which is being tackled first, then as much as 8500 m in the western one – in other words almost the entire distance – with the TBM”, as Breidenstein explained. “In this way we can produce the Boßler Tunnel with plenty of time to spare and also reckon with substantial savings worth many millions”.

x

Related articles:

Issue 04/2015 Germany

Boßler Tunnel: 1000 m excavated, mechanized Drive scheduled to be extended

The DB Projekt Stuttgart-Ulm GmbH is forging ahead with the construction of the Boßler Tunnel as planned. It is the longest tunnel on the new Wendlingen-Ulm rail route with a length of 8806 m. The...

more
Issue 08/2014 Germany?/?New Wendlingen–Ulm Route

Symbolic Starting Shot for the mechanized Drive of the Boßler Tunnel

The christening of the “Käthchen” tunnel boring machine (TBM) on November 8, 2014, marked the symbolic starting shot for driving operations on the Boßler Tunnel at the Aichelberg portal. From...

more
Issue 04/2017 Germany

Boßler Tunnel: TBM commenced Building the second Tunnel Tube

Käthchen, the tunnel boring machine (TBM), which the DB Projekt Stuttgart–Ulm GmbH is using to drive the Boßler Tunnel on the new Wendlingen–Ulm rail route, embarked on its second shield passage...

more
Germany

Boßler Tunnel: TBM commenced building the second Tunnel Tube

Käthchen, the tunnel boring machine (TBM), which the DB Projekt Stuttgart–Ulm GmbH is using to drive the Boßler Tunnel on the new Wendlingen–Ulm rail route, embarked on its second shield passage...

more
Issue 07/2015

The Boßler Tunnel – the longest Tunnel on the new Line Wendlingen–Ulm

Overview of the overall Project The Stuttgart–Ulm rail project is divided into the project sections Stuttgart–Wendlingen (Stuttgart 21) and the new line Wendlingen–Ulm. The project section...

more