„Semmering Base Tunnel New” – Securing the Precut with Self‑Drilling Anchors
In April 2012, work started on one of the most ambitious construction projects of Austria’s ÖBB-Infrastruktur AG: the New Semmering Base Tunnel. Scheduled for completion in 2024, the 27.3 km long tunnel through the Semmering range will cut the journey time on the south railway connecting Lower Austria and Styria. Before construction can begin at the entrance portal and tunnel bores, work concentrates on the above-ground sections with the clearance and excavation of the entrance ramp site. The slope is currently being excavated. The cut face is shored up with shotcrete and permanent self-drilling anchors, a perfect and economical bolting solution for softer rock formations. After completing the surface construction work, the twin-bore, single-track tunnel will be cut through the Semmering by conventional and continuous excavation beginning in 2015.
Once completed, the New Semmering Base Tunnel will be one of the longest rail tunnels in Austria. It will act as a vital link on the route crossing Europe’s heartland from Northern Germany to Italy, which currently has to climb the steep Semmering pass between Gloggnitz and Mürzzuschlag on a historic mountain railway recognized as one of the UNESCO World Heritage sites. The old route imposes considerable limitations on heavy freight transport, and passenger trains have to slow down to a speed of around 50 km/h. The New Semmering Base Tunnel will bypass this bottleneck and cut the journey time between Vienna and Graz by 30 min. It represents a particular advantage for freight traffic, since the new route’s minimal incline of 8.4 % removes all obstacles for even heavy freight trains.
Preparing the Tunnel Entrance Precut
Construction on the new route started in early 2012 with preliminary work on securing the entrance slopes in the Gloggnitz section by the Baubeteiligungsgesellschaft m.b.H. (BBG), Graz, Austria. For shoring up the cut face, BBG relies on permanent self-drilling anchors type Minova MAI (Minova MAI GmbH, Feistritz/Drau, Austria). “We have worked with Minova several times already, and we are very satisfied with the excellent advice and the flexibility that Minova has given us”, as the Managing Director of BBG, Franz Schweighofer, explains. The excavation of the precut proceeds by the so-called pilgrim steps process, in which cuts of a horizontal length of 6 to 10 m and height of 2 m are made with blocks of soil of similar dimensions remaining in place between each cut. The cuts are then secured with shotcrete and self-drilling anchors before moving on to the next sequence. The already mentioned permanent self-drilling anchors are CE-certified and are a particularly effective means for such bolting in soft or sandy rock formations.
Anchoring for Stability
For more efficient anchoring, BBG relies on a semi-mechanized setting process that uses an integrated rotary injection adaptor (IRIA). In this method, the hollow-rod anchors with lost (sacrificial) drill bit act as their own drill. Depending on the ground conditions, a cementitious grout or resin is pneumatically injected into the rod during drilling. Once the planned depth has been reached, a specialized anchoring grout is fed through the rod, which hardens to a concrete strength sufficient to bear the intended loads. A selection of drill bits is available to match the geological properties at the destination: the varied geology of the Gloggnitz site meant that the entire drill bit range provided by Minova MAI is being used. With a precut of around half a km in length and a cut height of approx. 10 m, the site uses around 1,600 permanent self-drilling anchors at lengths of 8 to 12 m, arrayed in a 1.5 x 1.5 m grid. 5,000 m² of shotcrete covers the new slope’s surface.
Tunneling to Begin in 2015
The New Semmering Base Tunnel will house 2 parallel shafts, each measuring 10 m in diameter. The twin bores will be spaced at a distance of 40 to 70 m from each other and connected by cross-passages every 500 m to act as escape routes in the event of emergency. The geological challenges of the chosen tunnel route mean that the tunnelling work commencing in 2015 will rely on 2 means of drivage: conventional tunnelling by excavation and blasting according to the New Austrian Tunnelling Method (NATM), and continuous excavation with tunnel boring machines (TBMs). Almost 28 km of tunnel will be cut for the New Semmering Base Tunnel, proceeding in multiple sections from both ends of the route until the 2 shafts meet far beneath the Semmering.
Powering on Through the Alps
The current plans envision the tunnelling work to be finished and the shafts ready by 2020. Once fully furnished and equipped, passenger and freight trains can begin to pass through the New Semmering Base Tunnel at speeds of up to 230 km/h at the end of 2024.