Switzerland

Roveredo Bypass: Tunnel Breakthrough

A 2-lane bi-directional tunnel is being built for the Roveredo Bypass – with shoulders at both sides and 2 lay-bys. It has up to 3,000 m overburden and runs north with 0.8 % gradient lying in an arc with a radius of more than 1,000 m. It is roughly 2.6 km long and possesses an equally long evacuation and rescue tunnel with 7 cross-passages, 2 of which are accessible with vehicles from the 2 lay-bys. If required, this heading is to be developed as a second, 2-lane tunnel bore with directional traffic. Controllable flaps are set up at 100 m gaps in the intermediate ceiling above the 11.5/18.0 m wide and 11 m high carriageway connected to the ventilation control centre at the south portal to remove smoke in the event of fire in the tunnel. The construction activities on the Roveredo Tunnel began on the rise with an exploratory heading in the tunnel axis from the south portal. The 4 m cutterhead diameter tunnel boring machine that was applied then tackled the parallel evacuation and rescue tunnel – with the rock being secured in both structures with shotcrete and in part with rock anchors. Some 2,100 m of tunnel was excavated (roughly 400 m of tunnel has been produced by cut-and-cover) after only 21 months by drill+blast thanks to the deployment of a novel drilling jumbo (with 3 drilling arms and a loading basket). After installing the seal, 2 formwork cars were applied to build the inner shell with up to 2.5 kg PP fibres/m³ being added to the concrete for fire protection purposes.
Work commenced in April 2009 at the south portal and the tunnel bore was broken through in November 2012. The rough construction operations are due to be concluded in 2014 and the tunnel is scheduled to be opened as part of national highway N13 in 2016. 120 million CHF (roughly 100 million €) has been earmarked for building the project.⇥G.B.

x

Related articles:

Issue 07/2012 Switzerland

Küblis Bypass: More than 60 % of Tunnel excavated

The Küblis Bypass scheme belongs to the Dalvazza-Selfranga project. Firstly the Klosters Bypass was opened in 2005 and then the Saas Bypass in 2011; now the 3,350 m long Küblis Bypass between...

more
Issue 06/2009 Formwork Technology

Stable Tunnel Formwork Carriage with flexible Design

A large number of infrastructural schemes are being executed in the region for the 2014 Winter Olympics to be held in the Black Sea resort of Sochi. These include a roughly 13??km long bypass for the...

more
Issue 03/2018 Switzerland

Gubrist Tunnel, Third Bore

The 3.3 km long Gubrist Tunnel is part of Zurich’s North Bypass between the communities of Weiningen and Regensdorf. The road tunnel began operating in 1985 and possesses two separate directional...

more
Issue 08/2014 Austria

Koralm Tunnel: Safety during Construction and Operation

The 32.9 km long Koralm Tunnel between Frauental on the Laßnitz in Styria and St. André in Carinthia represents the core of the 127 km long Koralmbahn railway between Graz and Klagenfurt. The...

more
Issue 02/2012 Switzerland

Saaser Tunnel – Saas Bypass opened

The 3.7 km long Saas Bypass on the A28 national highway with the 2.6 km long, 2-lane Saaser Tunnel (= 69 % of the route) and the parallel 2.3 km long safety tunnel was opened on October 21, 2011...

more