Rastatt Tunnel –Findings after Driving 1000 m

Work started on the first tube of the Rastatt Tunnel on the new/upgraded Karlsruhe–Basle rail route at the end of May 2016 as scheduled. After the so-called “flying shield start-up” for the tunnel boring machine (TBM) and penetrating the jet grouted sealing block adjoining the construction pit, the Tunnel Rastatt JV (Ed. Züblin AG and Hochtief Solutions AG) was able to commence standard operation. After 100 m had been driven, the federal highway 36 was successfully undertunnelled and then the frozen section in the Federbach low-lying area accomplished. The first 1000 m was excavated by mid-September at an average gross rate of advance of 11 m per day. This article follows up on the project report contained in tunnel 1/2016 on building the roughly 4.3 km long Rastatt rail tunnel.

Start of Driving in the east Tube

The driving of the Rastatt Tunnel’s east tube commenced at the end of May 2016 from the starting pit to the east of Ötigheim into the adjoining jet grouted sealing block. Prior to the TBM entering natural soil, this is where the first compressed air intervention took place in order to check the functional capacity of the aggregates and control the state of wear of the cutting tools as well as the cutting wheel on account of the in principle increased abrasiveness of the sealing block. The functional capacity was confirmed. No wear giving rise to concern was...

Related articles:

Issue 01/2016

Rastatt Tunnel: Strict Demands placed on mechanized Tunnelling

Overview of the Overall Project and Targets The new/upgraded Karlsruhe-Basle rail route is a part of the European freight corridor Rotterdam–Cologne–Basle–Milan–Genoa as well as the...

more
Issue 08/2015 Germany

First Tunnel Boring Machine approved for Rastatt Tunnel

The first of two tunnel boring machines (TBMs) for the Rastatt Tunnel by manufacturer Herrenknecht was approved by the customer, the Tunnel Rastatt JV, on December 8, 2015 at the factory in Schwanau....

more
Issue 04/2017 Germany

Boßler Tunnel: TBM commenced Building the second Tunnel Tube

Käthchen, the tunnel boring machine (TBM), which the DB Projekt Stuttgart–Ulm GmbH is using to drive the Boßler Tunnel on the new Wendlingen–Ulm rail route, embarked on its second shield passage...

more
Germany

Boßler Tunnel: TBM commenced building the second Tunnel Tube

Käthchen, the tunnel boring machine (TBM), which the DB Projekt Stuttgart–Ulm GmbH is using to drive the Boßler Tunnel on the new Wendlingen–Ulm rail route, embarked on its second shield passage...

more
Issue 08/2015 Germany

TBM in the Filder Tunnel has completed the first Shield Drive

The tunnel boring machine (TBM) driving the Filder Tunnel as part of the Stuttgart 21 infrastructure project has completed its first drive in the middle of November 2015. The Filder Tunnel (PfA 1.2)...

more