Project Stuttgart–Ulm: The Albaufstieg Tunnels – Construction Methods and contractual Characteristics

Single-track bores over a length of 28.7 km have to be driven for the 3 tunnels for the Albaufstieg. Together with a complex bridge construction, they form the 15.77 km long Albaufstieg of the sophisticated Stuttgart–Ulm major project. This report examines the construction methods and contractual aspects.

The Albaufstieg

The Albaufstieg links the slightly rising Albvorland area with the Alb high plateau. The entire “Alb­aufstieg” construction section by and large overcomes a height of 326 m in tunnels over a length of 15.77 km. From north west to south east the route first runs in the open as a short ramp with 31 ‰ and over a railway crossing to the portal of the Boßler Tunnel (Fig. 1). The route alignment of the 2 tracks expands to reach a centre distance of 30 m to create 2 single-bore tunnels.

The 8,806 m long Boßler Tunnel rises continuously over almost its entire length with 25 ‰. The entire...

Related articles:

Issue 04/2017 Germany

Boßler Tunnel: TBM commenced Building the second Tunnel Tube

Käthchen, the tunnel boring machine (TBM), which the DB Projekt Stuttgart–Ulm GmbH is using to drive the Boßler Tunnel on the new Wendlingen–Ulm rail route, embarked on its second shield passage...

more
Germany

Boßler Tunnel: TBM commenced building the second Tunnel Tube

Käthchen, the tunnel boring machine (TBM), which the DB Projekt Stuttgart–Ulm GmbH is using to drive the Boßler Tunnel on the new Wendlingen–Ulm rail route, embarked on its second shield passage...

more
Issue 04/2015 Germany

Boßler Tunnel: 1000 m excavated, mechanized Drive scheduled to be extended

The DB Projekt Stuttgart-Ulm GmbH is forging ahead with the construction of the Boßler Tunnel as planned. It is the longest tunnel on the new Wendlingen-Ulm rail route with a length of 8806 m. The...

more
Issue 08/2014 Germany?/?New Wendlingen–Ulm Route

Symbolic Starting Shot for the mechanized Drive of the Boßler Tunnel

The christening of the “Käthchen” tunnel boring machine (TBM) on November 8, 2014, marked the symbolic starting shot for driving operations on the Boßler Tunnel at the Aichelberg portal. From...

more
Issue 04/2014 Germany

Albaufstieg: 5 km of Tunnel already driven

The Stuttgart 21 project plans the creation of two additional tracks on the Stuttgart-Ulm-Augsburg route for a top speed of 250 km/h. The altogether 60 km long new route between Wendlingen and Ulm...

more