Austria/Slovenia

Karawanken Tunnel Redevelopment

Based on the state treaty between Austria and former Yugoslavia dating from 1977, the Austrian and Slovenian motorway operators, ASFINAG and DARS agreed in mid-April 2015 to jointly finance and execute the complete redevelopment of the almost 7.9 km long Karawanken Tunnel on the Karawanken Motorway (A11). In the first development phase the tunnel will be provided with a second bore, subsequently it is planned to redevelop the existing tube. The complete redevelopment of the Karawanken Tunnel featuring two tunnel tubes is due to be finished in 2023. As a result, construction work must be embarked on in autumn this year. The ASFINAG must first complete the area in front of the future portal, some 600 m including almost 350 m of bridge. The tunnel start-ups are scheduled at both sides for December 2017. Austria will contribute about 185 million euros of the total costs of 325 million euros with the Slovenian section accounting for an investment of roughly 140 million euros.

Since 2006 money has been constantly invested in the safety technical equipping of the Karawanken Tunnel’s existing tube. For example, up until spring 2015 the ASFINAG renewed the ventilation and ventilation control system. The Slovenian DARS improved the video detection system on its side and replaced all doors and gates.⇥

G. B./M. K.

x

Related articles:

Issue 05/2018 Austria/Slovenia

Karawanken Tunnel: ASFINAG starts Construction of the second Tube

On September 18, 2018, ASFINAG (Austrian Motorway Authority) heralded in the complete further development of the Karawanken Tunnel with the ground-breaking ceremony on the A 11 Karawanken motorway....

more
Issue 02/2017 Austria

Kärnten: Tunnel Safety given Priority for current Investments

Traffic safety, relieving congestion and maintaining the existing infrastructure represent the aims of the Austrian state-owned motorway operator ASFINAG. This year the company is investing no less...

more
Issue 02/2024 Austria/Slovenia | Österreich/Slowenien

Karawanken Tunnel Breakthrough

On 18 March 2024, the official tunnel breakthrough of the 2nd tube of the Karawanken Tunnel between Austria and Slovenia took place. This marks the completion of the tunnelling work on the 7.9 km long...

more
Austria/Slovenia

Karawanken Tunnel Breakthrough

Completion of the 2nd Bore Planned for Autumn 2025 This means that the inner lining of the new tunnel can begin in May 2024, followed by the installation of electrical equipment and safety systems....

more
Issue 05/2016 Austria/Slovenia

Karawanken Tunnel Portals: Design Contest concluded

The new construction of the Karawanken tunnel is picking up speed also from an architectural point of view. The tunnel construction is scheduled to start at the end of 2017 or beginning of 2018. The...

more