Switzerland

Gotthard Road Tunnel: Second Tube to be built from 2020

Following a resolution by the Swiss Federal Council dated October 25, 2017, the Federal Roads Office (FEDRO/ASTRA) will draw up a plan for executing the second Gotthard Road Tunnel tube, which will be presented to the Swiss Department for Environment, Transport, Energy and Communications (DETEC/UVEK) for approval. According to the current level of planning, construction work will commence in 2020 at the earliest.

After the referendum from February 2016, the Swiss Federal Council established the rough planning and the most essential benchmarks for the Gotthard Road Tunnel in the form of the “General Project”. In keeping with this plan, the second tunnel tube will be driven through the Gotthard Massif parallel to the existing roughly 17 km long tunnel at a gap of some 70 m. The two portal structures in Göschenen and Airolo as well as the four existing ventilation shafts will be utilised.

The implementation project will be passed on to the DETEC for approval – including the legal processing of any objections. Work on the second tube is due to start in 2020 at the earliest in keeping with the current level of planning. Roughwork will probably be finished by 2025 and the second tube will presumably be opened in late 2027 after all furnishings and tests are concluded. According to the latest forecast the project will cost around 2 billion Swiss francs (roughly 1.7 billion euros).

Once the second tube is completed, all traffic will run through it bidirectionally so that the existing tunnel can be redeveloped from 2028 till 2030. Then the two tubes will become unidirectional in accordance with the constitutional resolution governing Alpine conservation. One lane per direction will be reserved for traffic, the other serving as breakdown lane. This will result in a maximum capacity of 1000 car units per hour, corresponding to the capacity of the existing tunnel. Thanks to the exclusion of two-way traffic in the Gotthard Road Tunnel, safety will be substantially enhanced in comparison to today as frontal and grazing collisions will be avoided.

G.B.

x

Related articles:

Issue 03/2020 Switzerland | Schweiz

Gotthard Road Tunnel 2nd Bore: Start of Preparatory Work in Summer 2020

In December 2019, the Swiss Federal Department of the Environment, Transport, Energy and Communications (DETEC) examined the implementation project for the construction of the second Gotthard tube and...

more
Issue 02/2016 Switzerland

Gotthard Road Tunnel: „Yes“ to Second Bore

On February 28, 2016, a referendum held in Switzerland narrowly decided in favour of building a second bore for the Gotthard Road Tunnel, which links Göschenen in Canton Uri with Ariolo in Ticino....

more
Issue 05/2022 Switzerland

Gotthard Road Tunnel: Main Northern Lot of the Second Tube Awarded

The Swiss Federal Roads Office (FEDRO) has announced its decision to award the Gotthard main northern section to the JV “secondo tubo” (Implenia 60%/Frutiger 40%). The order for the 7.9 km long...

more
Switzerland

Gotthard Road Tunnel: Main Northern Lot of the Second Tube Awarded

The core element of the work is 7.3 km of tunnelling, at a diameter of 12.3 m, using a tunnel boring machine (TBM) and segmental lining. This connects to a 160 m long stretch at the start which will...

more
Issue 02/2021 Switzerland | Schweiz

2nd Gotthard Tube: Access Shaft Contract Awarded

In mid-March 2021, the Swiss Federal Roads Office (FEDRO) has awarded the 86.6 million Swiss francs (78.5 million euros) contract to build a 4 km access shaft for the second Gotthard tube (Lot 243)...

more