Switzerland

Ceneri Base Tunnel: Drive towards the South completed

On March 30, 2015, the tunnellers broke through the final few metres of the Ceneri Base Tunnel’s east bore between Sigirino and Vezia. Some two weeks after the first breakthrough in the west bore on March 17, which took place 13 months earlier than scheduled, this signifies that both southbound single-track tunnels for the tunnel have been excavated. Some 400 m away from the south portal in Vezia more than 600 persons involved in the project, watched on as the precise breakthrough for the west bore towards the south took place: the deviation was extremely minimal – amounting to 2 cm horizontally and 1 cm vertically. Currently the northbound drives are forging ahead. In the west bore around 1500 m must be excavated, with some 2000 m still to be accomplished in the east bore. The  main breakthrough is scheduled for early 2016. According to Renzo Simoni, the CEO of the AlpTransit Gotthard AG, the scheduled deadline for opening the tunnel remains December 2019.

x

Related articles:

Issue 01/2016 Switzerland

Breakthroughs in both Ceneri Base Tunnel Tubes

The main breakthrough took place in the western bore of the Ceneri Base Tunnel on January 21, 2016. Shortly after this final round of blasting the tunnellers were able to exchange handshakes. The...

more
Issue 04/2009 Switzerland

Ceneri Base Tunnel

The ramps of the present-day rail routes at the Ceneri amount to up to 26 %o - the same gradients that are to be found at the Gotthard. The building of the Gotthard Base Tunnel alone would not have...

more
Issue 04/2015

Ceneri Base Tunnel: Current Construction Status and Prospects

1 Description of the Project By creating the first virtually level rail route through the Alps, the NRLA opens up exciting new perspectives for rail transport. Freight can then be transported...

more
Issue 04/2011

Ceneri Base Tunnel: Stage reached by Work

1 Introduction The Ceneri Base Tunnel passes through Monte Ceneri over a length of 15.4 km. The overburdens amount up to 800 m. The route alignment takes the geological and topographical conditions...

more
Issue 04/2010

Ceneri Base Tunnel

Significance of the Ceneri Base Tunnel The ramps of the present railway route at the Ceneri possess gradients of up to 26 ‰. If the Ceneri Base Tunnel were not to be built additional locomotives...

more