Switzerland

Implenia and Frutiger Win Contract for Sisikon Tunnel, Key Section of the Neue Axenstraße Project

In late June 2024, the cantons of Schwyz and Uri have awarded the contract for the Sisikon Tunnel – lot 200 of the “Neue Axenstrasse” project – to a joint venture (JV) between Implenia (60%) and Frutiger (40%). Its size and complexity make this lot the key section of the new road running along the eastern shore of Lake Uri/Lake Lucerne. The contract as a whole is worth more than 440 million euros.

4.4 km Long Road Tunnel Is Excavated by Drill and Blast

The contract centres on the single-tube, 4.4 km two-way road tunnel, which the JV will blast through the rock. The JV is also building various other underground structures such as access tunnels, passing places, ventilation hubs and exhaust ducts. With up to seven simultaneous tunnelling points and very tight space conditions, the job presents some unique challenges.

Overview of the “A4 Neue Axenstraße” project including the Sisikon Tunnel (dashed line, right)
Credit/Quelle: axen.ch

Overview of the “A4 Neue Axenstraße” project including the Sisikon Tunnel (dashed line, right)
Credit/Quelle: axen.ch
In addition to the tunnelling, various external works are being carried out by other Implenia civil engineering units, including the construction of a large gallery to protect against natural hazards. Around 2 million tons of excavated material will be produced by the various construction projects, most of which will be taken away by boat to a large renaturation project on the Reuss Delta in Flüelen. The order is subject to a consultation period lasting until the end of July 2024. Construction of the lot is scheduled to start in mid-2025, and the work should be completed by 2034.

x

Related articles:

Issue 03/2024 Switzerland | Schweiz

Implenia and Frutiger Win Contract for Sisikon Tunnel

In late June 2024, the cantons of Schwyz and Uri have awarded the contract for the Sisikon Tunnel – lot 200 of the “Neue Axenstrasse” project – to a joint venture (JV) between Implenia (60%) and...

more
Issue 05/2022 Switzerland

Gotthard Road Tunnel: Main Northern Lot of the Second Tube Awarded

The Swiss Federal Roads Office (FEDRO) has announced its decision to award the Gotthard main northern section to the JV “secondo tubo” (Implenia 60%/Frutiger 40%). The order for the 7.9 km long...

more
Switzerland

SBB Awards Contract for Tunnel Ligerz, Lot 2, to Joint Venture Led by Implenia

In addition, four escape tunnels, a 114 m long viaduct for the exit of highway N5 and various additional structures are being built. The excavated material will be transported by ship and the existing...

more
Switzerland

Gotthard Road Tunnel: Main Northern Lot of the Second Tube Awarded

The core element of the work is 7.3 km of tunnelling, at a diameter of 12.3 m, using a tunnel boring machine (TBM) and segmental lining. This connects to a 160 m long stretch at the start which will...

more
Issue 04/2023 Switzerland | Schweiz

SBB Awards Contract for Tunnel Ligerz, Lot 2, to Joint Venture Led by Implenia

The SBB contract for lot 2 “Tunnel Ligerz” was assigned to joint venture IBD, consisting of the partners Implenia (lead), Bernasconi and De Luca. The total contract volume is 230 million euros. The...

more