Austria

Hydro and Solar Power Supply Electricity for Tunnel Operation

ASFINAG in Carinthia will begin implementing a further major expansion of renewable energy sources in the fall of 2023, with the aim of being self-sufficient in electricity by 2030. Work on the expansion of the existing photovoltaic systems at the Villach and Klagenfurt sites is scheduled to begin in November. Also in late autumn, construction work will start on a small hydropower plant directly at the Karawanken Tunnel, which will supply up to a third of the tunnel's energy requirements. And in spring 2024, another tunnel will be equipped with a solar power installation. A new system will be installed at the east portal of the Ehrentalerberg Tunnel in Klagenfurt to supply the infrastructure with renewable energy.

“The energy transition can only succeed with a consistent expansion of photovoltaics, hydropower and wind power,” says ASFINAG CEO Hartwig Hufnagl. “With this initiative in Carinthia, we are taking another important step towards achieving our goal of being self-sufficient in electricity by 2030. We will therefore follow up with many more such projects.”

New Solar Power Installation for Ehrentalerberg Tunnel

A new solar power system will be installed at the east portal of the Ehrentalerberg tunnel from spring 2024. More than 2600 solar electric panels with a total output of 1100 kilowatts peak will ensure that the tunnel can be operated in an energy-neutral manner in future. Completion is scheduled for the end of 2024.

Diverted Karawanken Mountain Waters Supply Electricity

Construction work on ASFINAG's third small hydropower plant has already started in 2023. Normally, tunnel seepage water is diverted from a tunnel without being utilised. In the case of the Karawanken tunnel, all this mountain water will be collected and channelled to the north portal, where it will be used to generate energy in a hydroelectric power plant. The mountain water is discharged very evenly throughout the year, which means that it can be expected to operate continuously for 60 years or more. The output of the power plant will be around 470 megawatt hours, which is as much as around 100 single-family homes need per year. The electricity generated will be fed directly into the tunnel. Around 30 per cent of the electricity required – not including ventilation – can be covered by hydropower in future.

x

Related articles:

Issue 06/2023 Austria | Österreich

Hydro and Solar Power Supply Electricity for Tunnel Operation

ASFINAG in Carinthia will begin implementing a further major expansion of renewable energy sources in the fall of 2023, with the aim of being self-sufficient in electricity by 2030. Work on the...

more
Issue 06/2019

Norway: Compact Hydro Tunnelling Offers Renewable Energy Solutions

A Haven for Hydropower Norway’s hydropower production capacity of 140 TWh covers more than 94% of the total electricity usage in the country. The vast majority of powerplants, however, were built...

more
Issue 03/2013 TBM tunnelling

Mechanized Excavation for the Chute de Gavet Hydropower Project in France

In the world-wide production of electricity, hydropower is in third place after coal and oil&gas. Therefore it is the most important renewable energy source and makes a significant contribution to the...

more
Issue 06/2013 Canada

Niagara Tunnel – providing renewable Power to Ontario for the next 100 Years

In March 2013, after eight years of tireless work, the largest hydroelectric project in Ontario in the past 50 years came to completion to the cheers of hundreds of onlookers. The new 10 km long...

more
Denmark/Germany

Green Energy for the Fehmarnbelt Tunnel

Constant Power Supply for the 18 km Fehmarnbelt Tunnel The largescale transformer station, which will be sited close to the tunnel portal at Rødbyhavn, will ensure that the 18 km Fehmarnbelt Tunnel...

more