Germany

Enlargement of the Fachinger Tunnel Successfully Completed

Between Diez and Fachingen, Porr is upgrading the 426 m long, double-track Fachingen Tunnel, which dates back to the 19th century. On behalf of Deutsche Bahn, Porr is working in a consortium with Feldhaus Bergbau GmbH & Co. KG and Heinz Schnorpfeil Bau GmbH. The tunnel cross-section has to be widened in order to guarantee the prescribed clearance gauge. In addition, the track spacing will be increased to 4 m. The enlargement is being carried out using the tunnel-in-tunnel method. On November 21, 2024, the tunnel enlargement system (TES) “Nora” breached the breakthrough wall of the Fachinger Tunnel. This milestone marked the end of the 380-metre-long conventional widening of the 160-year-old tunnel during ongoing rail operations.

On November 21, 2024, the “Nora” tunnel enlargement system breached the breakthrough wall of the Fachinger Tunnel
Credit/Quelle: Porr

On November 21, 2024, the “Nora” tunnel enlargement system breached the breakthrough wall of the Fachinger Tunnel
Credit/Quelle: Porr
The prevailing rock properties presented the tunnelling team with particular challenges. In order to cope with the changing geology of clay shale and keratophyre throughout the entire excavated cross-section, occasional blasting to loosen the rock was necessary during the excavation work. The excavated material fell next to the TES and was then removed by conveyor equipment. During the entire construction work, rail traffic continued to run safely under the protection of an enclosure on a newly laid track in the middle of the tunnel.

The Enlargement Work Is Followed by Concreting

Demolition of the breakthrough wall
Credit/Quelle: Porr

Demolition of the breakthrough wall
Credit/Quelle: Porr
The tunnelling team after the successful breakthrough
Credit/Quelle: Porr
The tunnelling team after the successful breakthrough
Credit/Quelle: Porr
After the breakthrough, “Nora” is pulled back to the site installation area. During this process, the sealing support is sprayed, the foundations are excavated, the blinding layer is concreted, drainage is installed and the foundations are concreted. As soon as the tunnel enlargement system has reached the installation area, it is dismantled. The concreting train is then lifted in to concrete the vault of the inner shell in cycles.

The narrow construction site in the local area and working while the railroad is in operation present particular challenges: “Due to the confined space in the tunnel, we can only use small machines that run on specially laid foundations and rails. In addition, great importance is attached to protecting the water in the catchment area of the 'Fachinger Brunnen' in Fachingen. That's why the monitoring is carried out precisely to the minute using state-of-the-art monitoring equipment,” says Folker Popp, Project Manager Tunnel Construction at Porr, explaining the special features of the construction site.

x

Related articles:

Germany

Enlargement of the Fachingen and Cramberg Tunnels

To widen the tunnel cross-sections, the two TES (tunnel enlargement systems) “Nora” and “Tilly von Cramberg” will work their way 426 and 732 metres through the mountain over the next few months....

more
Issue 01/2024 Germany | Deutschland

Enlargement of the Fachingen and Cramberg Tunnels

A total of six tunnels along the Lahntal railway line from Wetzlar to Koblenz are being renovated and modernised on behalf of Deutsche Bahn. After just under a year of preparation, tunnelling work...

more
Issue 05/2024 Herrenknecht

Turning Old Into New: Tunnel Enlargement During Operation

In the second half of the 19th and early 20th century, hundreds of railway tunnels were built in Europe. They are largely still in operation today. In the coming decades, a considerable number of...

more
Herrenknecht

Turning Old Into New: Tunnel Enlargement During Operation

Enlargement of the Fachingen and Cramberg Tunnel Profiles Two Tunnel Enlargement Systems have been in use since January 2024 for the renewal of Deutsche Bahn tunnels near Limburg an der Lahn. The...

more
Issue 02/2016 Qatar

Major Contract for Porr in Qatar: Building the Track for Doha Metro

Porr is forging ahead with the construction of the Green Line for the Doha Metro abreast of schedule for the client Qatar Railway Company. In late 2015, Porr was also commissioned to produce the solid...

more