Rail Technology in the Gotthard Base Tunnel

Untertiteltext Englisch

In May 2010 the installation of the rail technical equipment was scheduled to commence in the western bore between Bodio and Faido at the Gotthard Base Tunnel’s south portal. The rail tunnel will be completely equipped and ready to cope with rail services by 2017. In this way the final stage in accomplishing this project of the century has been embarked on.

The rail technology embraces all components and systems, which belong to the “actual rail technical system”: the track, electric installations for supplying power for the rail technology and the tunnel, rail power installations for traction current, Telecom equipment, safety and automation installations. These facilities will enable rail services in the 2 single-track tunnels of the Gotthard Base Tunnel and link up the new tracks with the existing railway network. Rail services with peak speeds of up to 250 km/h will first become possible thanks to the rail technology thus accomplishing the...

Related articles:

Issue 01/2015 Switzerland

Gotthard Base Tunnel: Track Installation completed

At the end of October 2014 the final sections of track were laid in the Gotthard Base Tunnel (GBT). This means that the world’s longest rail tunnel can now be negotiated over its entire 57 km length...

more
Issue 04/2011

Rail Technology for the Gotthard Base Tunnel

The first Swiss north-south high-speed route between Zurich and Milan including the Gotthard and Monte Ceneri tunnels is some 90 km long. Since 2009 work on installing the rail technology in the...

more
Issue 08/2011 Switzerland

Gotthard Base Tunnel Installation of Rail Technology started from the North

Work has commenced on the installation of the rail technology for the Gotthard Base Tunnel (GBT) for the north as well. On September 2, 2011 Renzo Simoni, CEO of the AlpTransit Gotthard AG (ATAG),...

more
Issue 06/2017 Switzerland

Ceneri Base Tunnel – Installation of Railway Equipment has begun

At the north portal of the Ceneri Base Tunnel, installation of railway equipment in the east bore started in summer 2017. The 15.4 km long base tunnel between Camorino and Vezia will be equipped in...

more
Issue 03/2011 Switzerland

Gotthard Base Tunnel: Drive concluded

On March 23, 2011 at 20 past 12 noon the tunnel boring machine broke through from the Faido western bore into the Sedrun part-section (title page); in this connection the deviations from the intended...

more